Isiolo Dashboard
|
Project Type | Project Name | Objective | Estimated Cost | Planned start date | Planned end date | Status |
---|---|---|---|---|---|---|
Project Type | Project Name | Objective | Estimated Cost | Planned start date | Planned end date | Status |
County | Kijito water supply rehabilitation | To strengthen sustainable water resource management, supply and sanitation services that enhance accessibility to clean safe and affordable water | Ksh. 4,000,000.00 | 2022-01-05 | 2022-03-05 | Completed |
County | Construction of Iresaboru 50m3 tank at town centre | To strengthen sustainable water resource management, supply and sanitation services that enhance accessibility to clean safe and affordable water | Ksh. 4,000,000.00 | 2022-02-16 | 2022-04-28 | Completed |
County | Rehabilitation of 50m3 Iresaboru elevated steel tank at Borehole source | To strengthen sustainable water resource management, supply and sanitation services that enhance accessibility to clean safe and affordable water | Ksh. 4,000,000.00 | 2022-02-17 | 2022-06-08 | Completed |
County | Mataarba 50m3 elevated steel tank construction | To strengthen sustainable water resource management, supply and sanitation services that enhance accessibility to clean safe and affordable water | Ksh. 4,000,000.00 | 2022-01-06 | 2022-05-19 | Completed |
County | Borehole maintenance | To strengthen sustainable water resource management, supply and sanitation services that enhance accessibility to clean safe and affordable water | Ksh. 3,000,000.00 | 2021-09-15 | 2022-03-08 | Completed |
County | Ngaremara water supply Project-Masonry tank construction | To strengthen sustainable water resource management, supply and sanitation services that enhance accessibility to clean safe and affordable water | Ksh. 3,000,000.00 | 2018-12-06 | 2019-06-06 | Completed |
County | Ngaremara water supply Project-Pipeline Extension | To strengthen sustainable water resource management, supply and sanitation services that enhance accessibility to clean safe and affordable water | Ksh. 4,000,000.00 | 2018-07-02 | 2019-06-11 | Completed |
County | Isiolo County Headquarters | To improve Governance and administrative capacity | Ksh. 55,000,000.00 | 2018-11-20 | 2021-06-17 | Ongoing |
County | Procurement and equipping of 3 Ambulances | To improve health service efficiency | Ksh. 36,000,000.00 | 2020-06-02 | 2022-06-30 | Ongoing |
County | Construction and equipping of Accident and Emergency Centre at ICTRH | To improve health service delivery | Ksh. 90,000,000.00 | 2020-03-02 | 2022-06-06 | Planned |
County | UHC in Isiolo County | To improve health service efficiency | Ksh. 559,700,000.00 | 2021-06-15 | 2021-06-15 | Ongoing |
County | Local Physical development plans for Kambi Asharaf, Kambi Juu, Kambi juu II, Kinna Maishabora and Shambani | To have well planned and organized spaces with clearly defined land uses and boundaries | Ksh. 9,000,000.00 | 2018-06-12 | 2020-06-16 | Ongoing |
County | Sericho borehole water project (Borehole drilling, equipping with solar, lay 1.6km pipeline, 1new kiosk and fencing) | To strengthen sustainable water resource management, supply and sanitation services that enhance accessibility to clean safe and affordable water | Ksh. 9,000,000.00 | 2022-06-20 | 2022-06-20 | Completed |
Ward | Sericho Water and Sanitation Project | To strengthen sustainable water resource management, supply and sanitation services that enhance accessibility to clean safe and affordable water | Ksh. 9,000,000.00 | 2018-12-06 | 2019-03-28 | Completed |
Ward | Ngabilabia Water and Sanitation Project | To strengthen sustainable water resource management, supply and sanitation services that enhance accessibility to clean safe and affordable water | Ksh. 13,790,000.00 | 2017-12-08 | 2018-12-07 | Completed |
Ward | Awarsitu Water and Sanitation Project –Borehole works | To strengthen sustainable water resource management, supply and sanitation services that enhance accessibility to clean safe and affordable water | Ksh. 13,320,000.00 | 2017-12-08 | 2019-03-31 | Completed |
Ward | Ngaremara water supply Project-borehole drilling | To strengthen sustainable water resource management, supply and sanitation services that enhance accessibility to clean safe and affordable water | Ksh. 1,560,000.00 | 2019-07-01 | 2022-06-30 | Completed |
Village | Iresaboru livestock borehole equipping with Solar pumping system | Enhancing water supply and storage | Ksh. 3,000,000.00 | 2019-01-14 | 2019-06-14 | Completed |
Village | Provision of Generators for Sericho borehole | Enhancing water supply and storage | Ksh. 1,900,000.00 | 2019-01-07 | 2019-06-15 | Completed |
Village | Construction of 50 cu.m Elevated Steel Tank at Gubatu | Enhancing water supply and storage | Ksh. 3,900,000.00 | 2019-01-20 | 2019-06-15 | Completed |
Village | Renovation of tank and fixing inlets and outlets of Lenguruma Water supply | Enhancing water supply and storage | Ksh. 1,270,000.00 | 2019-01-20 | 2019-06-15 | Completed |
Village | Upgrading of Lenguruma Water supply mainline | To provide clean safe water to residents of Isiolo County | Ksh. 3,800,000.00 | 2019-01-20 | 2019-06-14 | Completed |
Village | Renovation of Nakuplat Water Supply in Ngaremara Ward | Enhancing water supply and storage | Ksh. 1,005,000.00 | 2019-01-20 | 2019-06-15 | Completed |
Village | Augmentation of Ngaremara water supply | Enhancing water supply and storage | Ksh. 3,100,000.00 | 2019-01-20 | 2019-06-25 | Completed |
Ward | Gotu Water Supply storages and distribution rehabilitation | Enhancing water supply and storage | Ksh. 1,300,000.00 | 2019-01-20 | 2019-06-15 | Completed |
Ward | Kulamawe pipeline extensions and construction of kiosks | To provide clean safe water to residents of Isiolo County | Ksh. 4,000,000.00 | 2019-01-23 | 2019-03-29 | Completed |
Village | Rehabilitation of Gafarsa Water Supply Pipeline | Enhancing water supply and storage | Ksh. 3,200,000.00 | 2019-02-20 | 2019-03-20 | Completed |
Village | Provision of Generators for Gafarsa borehole | Enhancing water supply and storage | Ksh. 4,000,000.00 | 2019-03-30 | 2019-06-15 | Completed |
County | Water related drought emergencies- Repair of broken down boreholes and provision of plastic tanks to water trucking centres | Enhancing water supply and storage | Ksh. 12,000,000.00 | 2018-07-30 | 2019-06-30 | Completed |
Ward | Provision of water meters | Enhancing water supply and storage | Ksh. 2,000,000.00 | 2019-03-20 | 2019-06-15 | Completed |
Village | Malkadaka Borehole drilling | Enhancing water supply and storage | Ksh. 2,700,000.00 | 2019-01-22 | 2019-06-15 | Completed |
Village | Construction of Elevated Steel Tank at Kombola | Enhancing water supply and storage | Ksh. 4,000,000.00 | 2018-09-11 | 2019-06-15 | Completed |
Village | Renovation of Muchuro water tank | Enhancing water supply and storage | Ksh. 1,510,000.00 | 2019-01-15 | 2019-06-15 | Completed |
Village | Garfasa tank renovations | Enhancing water supply and storage | Ksh. 1,300,000.00 | 2019-01-02 | 2019-06-15 | Completed |
County | Provision of borehole equipment and tools | Enhancing water supply and storage | Ksh. 2,000,000.00 | 2019-01-09 | Completed | |
Village | Modogashe water supply pipeline rehabilitations | To provide clean safe water to residents of Isiolo County | Ksh. 3,300,000.00 | 2019-01-07 | 2019-06-15 | Completed |
Village | Modogashe water supply pipeline rehabilitations | To provide clean safe water to residents of Isiolo County | Ksh. 3,300,000.00 | 2019-01-07 | 2019-06-15 | Completed |
Ward | Kiwanjani water pipe extension | To provide clean safe water to residents of Isiolo County | Ksh. 2,100,000.00 | 2019-01-07 | 2019-06-15 | Completed |
Ward | Drilling of Fire Engine at Ministry of Lands, Housing & Urban development Compound in Isiolo County | Enhancing water supply and storage | Ksh. 3,000,000.00 | 2019-01-22 | 2019-06-15 | Completed |
Ward | Extension of Sewer line in Kiwanjani Area | Improve onsite sanitation for rural community water points | Ksh. 1,000,000.00 | 2019-03-30 | 2019-06-15 | Completed |
Village | Merti borehole drilling | To provide clean safe water to residents of Isiolo County | Ksh. 3,300,000.00 | 2019-01-07 | 2019-06-30 | Completed |
Village | Malkagalla borehole drilling | To provide clean safe water to residents of Isiolo County | Ksh. 4,100,000.00 | 2019-01-07 | 2019-06-15 | Completed |
Village | Construction of Awarsitu 50cubic meters Water tank | Enhancing water supply and storage | Ksh. 3,200,000.00 | 2019-01-07 | 2019-06-15 | Completed |
Village | Awarsitu borehole drilling | Enhancing water supply and storage | Ksh. 4,000,000.00 | 2019-01-07 | 2019-06-15 | Completed |
Ward | Erimet borehole pipeline extension and borehole fencing equipping and extensions | Enhancing water supply and storage | Ksh. 1,500,000.00 | 2019-01-07 | 2019-06-15 | Completed |
Ward | Erimet Borehole equipping and extensions | Enhancing water supply and storage | Ksh. 3,500,000.00 | 2019-01-07 | 2019-06-15 | Completed |
County | purchase of assorted games items for the clubs 20/21 | To enhance empowerment and participation of youth and other vulnerable groups in all aspects of county development | Ksh. 1,600,000.00 | 2020-06-15 | 2021-06-15 | Completed |
County | purchase of assorted games items to the clubs | IMPOROVE SPORTS INFRASTRUCTURE IN THE COUNTY | Ksh. 1,600,000.00 | 2019-06-15 | 2020-06-15 | Completed |
County | Training of Bodaboda riders issuing reflectors and licenses | To enhance empowerment and participation of youth and other vulnerable groups in all aspects of county development | Ksh. 6,000,000.00 | 2019-06-15 | 2020-06-15 | Completed |
County | Training of 53 youths on entrepreneurship skills at KSG | Enhance youth skills and self-employment. | Ksh. 1,500,000.00 | 2019-06-15 | 2020-06-15 | Completed |
County | Training of youths on governance | To enhance empowerment and participation of youth and other vulnerable groups in all aspects of county development | Ksh. 2,500,000.00 | 2018-06-15 | 2019-06-15 | Completed |
County | Training of coaches and referees | IMPOROVE SPORTS INFRASTRUCTURE IN THE COUNTY | Ksh. 2,000,000.00 | 2018-06-15 | 2019-06-15 | Completed |
County | Repair of faulty water supplies in the County under drought support | Enhancing water supply and storage | Ksh. 800,000.00 | 2019-07-01 | 2019-12-30 | Completed |
Ward | Rehabilitation of Purkuk Water Pan in Oldonyiro ward, Isiolo County | Enhancing water supply and storage | Ksh. 3,000,000.00 | 2020-02-20 | 2020-06-15 | Completed |
Ward | Construction of extension of Manyatta Zebra Water supply | Enhancing water supply and storage | Ksh. 3,000,000.00 | 2020-04-14 | 2020-04-14 | Completed |
Village | Repair of Kinna CDF borehole, Rapsu borehole, Modogashe water supply | To provide clean safe water to residents of Isiolo County | Ksh. 1,200,000.00 | 2020-01-07 | 2020-06-15 | Completed |
Village | Repair of Duse and Toiboto boreholes | Enhancing water supply and storage | Ksh. 562,600.00 | 2019-12-01 | 2020-02-01 | Completed |
Ward | Procurement of generator for Jillo Dima borehole | To provide clean safe water to residents of Isiolo County | Ksh. 1,710,000.00 | 2020-01-07 | 2020-06-30 | Completed |
Ward | Purchase of water meters | Enhancing water supply and storage | Ksh. 1,500,000.00 | 2020-03-15 | 2020-06-15 | Completed |
Village | Spares for Malkadaka, Kombola, Manyatta Zebra and Kambi ya Juu boreholes | Enhancing water supply and storage | Ksh. 1,520,000.00 | 2020-01-15 | 2020-06-15 | Completed |
Ward | Rehabilitation of Iresaboru & Badana pipeline water supply | Enhancing water supply and storage | Ksh. 3,000,000.00 | 2019-11-01 | 2020-05-11 | Completed |
Ward | Drilling of Sheshelesi borehole | To provide clean safe water to residents of Isiolo County | Ksh. 2,000,000.00 | 2020-01-07 | 2020-06-15 | Completed |
Ward | Equipping of Fire Engine borehole | Enhancing water supply and storage | Ksh. 2,300,000.00 | 2020-01-07 | 2020-06-15 | Completed |
Ward | Extension of Almasi Childrens Home water supply | Enhancing water supply and storage | Ksh. 1,000,000.00 | 2020-03-01 | 2020-06-15 | Completed |
Ward | Repair of Belgesh , Garfasa, Malkadaka, Yakbarsadi and Garbatulla water supplies | Enhancing water supply and storage | Ksh. 2,500,000.00 | 2020-01-07 | 2020-06-30 | Completed |
Village | Borehole fencing and construction of pump house in Gafarsa | Enhancing water supply and storage | Ksh. 2,000,000.00 | 2020-01-07 | 2020-03-30 | Completed |
Ward | Drilling of Titu borehole | Enhancing water supply and storage | Ksh. 3,200,000.00 | 2019-09-15 | 2020-04-30 | Completed |
County | Procurement of water storage tanks and provison of portable steel platforms | Water trucking | Ksh. 2,000,000.00 | 2019-09-15 | 2020-04-30 | Completed |
County | Procurement of goods for strategic water supplies and communities under emergency water trucking in Isiolo county(as interventions for emergency borehole repairs during drought) | Enhancing water supply and storage | Ksh. 2,200,000.00 | 2020-01-06 | 2020-06-15 | Completed |
County | Supply of goods for repairs of various rural water supplies(as interventions for emergency borehole repairs during drought | Enhancing water supply and storage | Ksh. 3,500,000.00 | 2019-09-11 | 2019-12-30 | Completed |
County | Feasibility studies and hydrogeological surveys for Kuri, Titu, Bulla Mpya, Chehelesi, Merti,Biliqo marar, Malkadala | Enhancing water supply and storage | Ksh. 2,500,000.00 | 2019-11-01 | 2020-04-30 | Completed |
Ward | Repair of Alango/Basa and Kinna boreholes | Enhancing water supply and storage | Ksh. 750,000.00 | 2020-01-05 | 2020-06-05 | Completed |
Ward | Repair of Bertume, Godarupa boreholes and supply of fast moving spare parts( as interventions for emergency borehole repairs during drought) | To provide clean safe water to residents of Isiolo County | Ksh. 3,700,000.00 | 2020-01-05 | 2020-06-15 | Completed |
County | Establish Community grant | To support community driven food security initiatives | Ksh. 160,725,000.00 | 2019-07-02 | 2020-06-30 | Ongoing |
County | Training of women on financial literacy | Ksh. 1,000,000.00 | 2020-04-21 | 2020-04-25 | Completed | |
County | Training of sexual and gender based violence service provider on referral pathway | Ksh. 1,000,000.00 | 2020-09-10 | 2020-11-04 | Completed | |
County | Community Sensitization on child protection | Ksh. 1,000,000.00 | 2020-11-30 | 2020-12-04 | Completed | |
County | To provide drought tolerant seeds and seedlings | To increase crop production and productivity | Ksh. 10,000,000.00 | 2019-07-17 | 2020-06-10 | Completed |
County | Development of draft child protection action plan | Ksh. 1,000,000.00 | 2020-08-10 | 2021-03-25 | Completed | |
County | Development of isiolo county youth ,women ,and PWDs Enterprise Development Fund Regulation(amended 2021) | Ksh. 1,000,000.00 | 2020-07-21 | 2021-05-17 | Completed | |
County | Train farmers on proper management skills | Promotion of climate smart agriculture farming technologies | Ksh. 100,000.00 | 2019-07-10 | 2020-06-16 | Completed |
County | Development of strategic plan for enterprise development fund | Ksh. 1,000,000.00 | 2020-07-23 | 2021-06-10 | Completed | |
Village | Merti borehole fencing & Equipping | Enhancing water supply and storage | Ksh. 4,000,000.00 | 2019-09-01 | 2020-05-30 | Completed |
Ward | maintenance and spot improvement of roads within sericho ward - 20/21 | To improve accessibility and movement in the county | Ksh. 9,998,770.00 | 2020-12-30 | 2021-05-04 | Completed |
Village | Dadachabasa Elevated steel tank repairs | Enhancing water supply and storage | Ksh. 2,400,000.00 | 2020-02-20 | 2020-06-15 | Completed |
Village | Yamicha water supply rehabilitations | Enhancing water supply and storage | Ksh. 4,000,000.00 | 2020-03-01 | 2020-06-15 | Completed |
Ward | Merti Community water project spares | Enhancing water supply and storage | Ksh. 500,500.00 | 2020-04-15 | 2020-05-16 | Completed |
Ward | Drilling of Biliqo-Marara borehole in Merti Sub County of Isiolo County | Enhancing water supply and storage | Ksh. 3,000,000.00 | 2020-01-11 | 2020-06-30 | Completed |
County | Construction of Isiolo stadium phase 2 | IMPOROVE SPORTS INFRASTRUCTURE IN THE COUNTY | Ksh. 58,742,200.00 | 2019-06-15 | 2020-06-15 | Ongoing |
County | Repair of Ngarendare,Dogogicha and Gafarsa water supplies(as interventions for emergency borehole repairs during drought) | To repair faulty water supplies | Ksh. 1,750,000.00 | 2019-07-30 | 2020-05-30 | Completed |
County | Spring protection and catchment conservation at Baraka farm in Isiolo | To protect and conserve catchment areas | Ksh. 2,500,000.00 | 2019-07-15 | 2020-06-23 | Completed |
County | Disaster Risk Reduction measures | To ensure an effective and efficient preparedness and response to disasters | Ksh. 3,500,000.00 | 2020-07-07 | 2021-06-21 | Completed |
County | Promotion of fish value addition | To Increase fish consumption | Ksh. 200,000.00 | 2019-07-01 | 2020-06-30 | Ongoing |
County | Hosted international day of zero tolerance for FGM,International womens day and 16 days of activism | Ksh. 2,000,000.00 | 2019-02-07 | 2019-04-03 | Completed | |
County | construction and equipping of isiolo vet stores | enhance vet vaccines viability through cold chain improvement | Ksh. 1,000,000.00 | 2019-07-01 | 2020-06-30 | Completed |
County | Phase I Development of a Disaster Information Management System | To ensure effective and efficient flow of alert information on disasters | Ksh. 4,300,000.00 | 2020-07-01 | 2021-06-30 | Completed |
County | Construction of Ecde classroom in all wards | increase in access and retention | Ksh. 24,000,000.00 | 2018-09-11 | 2019-03-12 | Completed |
County | DRM policy development | To reduce the impact of disasters in the county | Ksh. 2,000,000.00 | 2020-01-06 | 2020-10-26 | Completed |
County | Organize 10th Edition of Annual Desert Wheel Race | Ksh. 25,000,000.00 | 2021-10-23 | 2021-11-03 | Planned | |
County | Sensitization and Elimination of SGBV,FGM and other harmful traditional practices | Reduce gender inequality at all levels of development | Ksh. 2,000,000.00 | 2019-08-08 | 2019-11-21 | Completed |
County | Hosted regional cultural festival | Enhancing heritage and culture knowledge, appreciation and conservation | Ksh. 2,000,000.00 | 2019-05-21 | 2019-07-03 | Completed |
County | Construction of VTCs at Oldonyiro and Sericho | To increase enrollment at VTCs | Ksh. 21,352,000.00 | 2018-09-11 | 2019-03-12 | Completed |
County | Coordinated and organised 8th edition of desert wheel race | Ksh. 5,000,000.00 | 2019-07-18 | 2019-11-06 | Completed | |
County | Development of Gender policy | Ksh. 5,000,000.00 | 2020-07-23 | 2021-12-15 | Ongoing | |
County | Arts and culture for peace 3 | Ksh. 2,000,000.00 | 2020-07-01 | 2021-06-30 | Completed | |
County | Arts and culture for peace 2 | Ksh. 2,000,000.00 | 2019-07-01 | 2020-06-30 | Completed | |
County | Training of EDF Board members, Committee and beneficiaries | Ksh. 1,000,000.00 | 2021-08-18 | 2021-08-22 | Completed | |
County | Art and culture for peace 1 | Ksh. 2,000,000.00 | 2018-07-01 | 2019-06-30 | Completed | |
County | Maintenance and spot improvement of roads within isiolo county- 18/19 | Upgrading the roads to ridable state | Ksh. 118,342,000.00 | 2019-01-04 | 2019-07-05 | Completed |
County | Capacity building 3 | Ksh. 6,000,000.00 | 2020-07-01 | 2021-06-30 | Completed | |
County | capacity building and policies | capacity buiding | Ksh. 4,200,000.00 | 2019-01-02 | 2020-12-03 | Completed |
County | Capacity building 2 | Ksh. 4,000,000.00 | 2019-07-01 | 2020-06-30 | Completed | |
County | Capacity building 1 | Ksh. 4,000,000.00 | 2018-07-01 | 2019-06-30 | Completed | |
County | Community dialogue meetings 3 | Ksh. 3,000,000.00 | 2020-07-01 | 2021-06-30 | Completed | |
Ward | Leparua irrigation scheme phase 1 | increase area under irrigation | Ksh. 1,500,000.00 | 2021-07-13 | 2022-09-13 | Planned |
County | Community dialogue meetings 2 | Ksh. 3,000,000.00 | 2019-07-01 | 2020-06-30 | Completed | |
Ward | Construction of Oldonyiro ward administrators office | Service delivery to citizens and amiable working environment | Ksh. 4,700,000.00 | 2018-07-02 | 2019-06-28 | Completed |
County | purchase of fire engine | purchase fire engine | Ksh. 58,000,000.00 | 2019-07-09 | 2020-06-09 | Completed |
County | Community dialogue meetings 1 | Ksh. 3,000,000.00 | 2018-07-01 | 2019-06-30 | Completed | |
Ward | Construction and extension of Esimit water supply | Enhance water supply and storage | Ksh. 2,000,000.00 | 2019-11-22 | 2020-03-30 | Completed |
County | Construction of Isiolo stadium phase 3 | IMPOROVE SPORTS INFRASTRUCTURE IN THE COUNTY | Ksh. 36,936,000.00 | 2020-06-15 | 2021-06-15 | Ongoing |
County | Drilling of Bulla Mpya borehole | Increase access to clean safe and affordable water | Ksh. 2,100,000.00 | 2019-11-08 | 2020-03-30 | Completed |
County | Disaster Information Management System | To reduce an impact of disasters through communication | Ksh. 4,300,000.00 | 2021-02-02 | 2021-11-02 | Ongoing |
County | DRM Policy Development | To reduce the impact of disasters and emergencies | Ksh. 3,000,000.00 | 2020-09-15 | 2021-06-16 | Completed |
Ward | Kilimani dam | To increase area under irrigation | Ksh. 127,016,000.00 | 2018-09-18 | 2021-07-14 | Ongoing |
County | cabro construction | construct cabro in identified selected sites in isiolo town | Ksh. 93,000,000.00 | 2019-05-06 | 2020-12-03 | Completed |
County | Youth, Women & PWDs Enterprise Development Fund Act | Economic empowerment of the vulnerable groups in the county with interest free loans | Ksh. 5,000,000.00 | 2021-10-29 | 2022-06-09 | Completed |
Ward | construction of Kinna cultural centre | Enhancing heritage and culture knowledge, appreciation and conservation | Ksh. 9,000,000.00 | 2020-06-09 | 2021-06-21 | Planned |
County | Development of county gender policy | Reduce gender inequality at all levels of development | Ksh. 3,000,000.00 | 2020-07-17 | 2021-06-15 | Ongoing |
County | Construction of bridges within the county | To improve accessibility and movement in the county | Ksh. 14,000,000.00 | 2020-12-30 | 2021-05-04 | Completed |
Ward | Maintenance and spot improvement of roads within Burat ward - 20/21 | Upgrading the roads to ridable state | Ksh. 19,519,100.00 | 2020-12-30 | 2021-05-04 | Completed |
Ward | maintenance and spot improvement of roads within bula pesa ward -20/21 | Upgrading the roads to ridable state | Ksh. 25,000,000.00 | 2020-12-30 | 2021-05-04 | Completed |
Ward | maintenance and spot improvement of roads within wabera ward - 20/21 | Upgrading the roads to ridable state | Ksh. 34,500,000.00 | 2020-12-30 | 2021-05-04 | Completed |
Ward | maintenance of roads within chari ward | Upgrading the roads to ridable state | Ksh. 9,999,980.00 | 2020-12-30 | 2021-05-04 | Completed |
Ward | maintenance of roads within cherab ward - 20/21 | Upgrading the roads to ridable state | Ksh. 9,999,990.00 | 2020-12-30 | 2021-05-04 | Completed |
Ward | maintenance and spot improvement of garbatulla ward roads -20/21 | Upgrading the roads to ridable state | Ksh. 9,999,960.00 | 2020-12-30 | 2021-05-04 | Completed |
Ward | maintenance and spot improvement of roads within Kinna ward - 20/21 | Upgrading the roads to ridable state | Ksh. 10,000,500.00 | 2020-12-30 | 2021-05-04 | Completed |
Ward | maintenance and spot improvement of roads within ngaremara ward - 20/21 | Upgrading the roads to ridable state | Ksh. 9,999,970.00 | 2020-12-30 | 2021-05-04 | Completed |
Ward | Maintenance and spot improvement of roads within oldonyiro ward -21 | Upgrading the roads to ridable state | Ksh. 10,000,800.00 | 2020-12-30 | 2020-12-30 | Completed |
Ward | maintenance and spot improvement of projects within Burat ward | Upgrading the roads to ridable state | Ksh. 13,997,800.00 | 2020-01-15 | 2020-05-14 | Completed |
Ward | spot improvement and maintenance of Bulapesa ward roads | Upgrading the roads to ridable state | Ksh. 20,788,800.00 | 2020-01-15 | 2020-05-14 | Completed |
Ward | maintenance and spot improvement of roads within wabera ward | Upgrading the roads to ridable state | Ksh. 12,290,800.00 | 2020-01-15 | 2020-05-14 | Completed |
Ward | Routine maintenance and spot improvement of garbatulla ward roads | Upgrading the roads to ridable state | Ksh. 15,005,400.00 | 2020-01-15 | 2020-05-14 | Completed |
Ward | Maintenance and spot improvement of Kinna Ward roads | Upgrading the roads to ridable state | Ksh. 18,547,300.00 | 2020-01-15 | 2020-05-14 | Completed |
Ward | Routine maintenance and spot improvement of Ngaremara ward roads | Upgrading the roads to ridable state | Ksh. 15,386,400.00 | 2020-01-15 | 2020-05-14 | Completed |
Ward | Maintenance and spot improve of oldonyiro ward roads | Upgrading the roads to ridable state | Ksh. 19,994,800.00 | 2020-01-15 | 2020-05-14 | Completed |
Ward | Maintenance and spot improvement of Sericho ward roads | Upgrading the roads to ridable state | Ksh. 19,999,900.00 | 2020-01-15 | 2020-05-14 | Completed |
County | Apiculture development | availing beehives to the community | Ksh. 2,000,000.00 | 2019-07-01 | 2020-06-30 | Completed |
County | Women groups grants | Reduce gender inequality at all levels of development | Ksh. 8.00 | 2021-09-23 | 2021-12-15 | Planned |
County | Establishment of youth innovation Centre | Enhance youth skills and self employment | Ksh. 4,969,400.00 | 2020-03-04 | 2020-09-26 | Completed |
Sub County | construction of kinna vet lab fence | fence construction around kinna vet lab | Ksh. 1,000,000.00 | 2019-07-01 | 2020-06-30 | Completed |
County | Development of county child protection legal framework | Ksh. 10,000,000.00 | 2020-07-22 | 2022-07-21 | Ongoing | |
County | market construction | construct modern international market | Ksh. 270,000,000.00 | 2019-05-06 | 2022-05-04 | Ongoing |
County | cold chain facilities | enhance vet vaccines viability through construction renovation of vet store | Ksh. 500,000.00 | 2019-07-01 | 2020-06-01 | Completed |
County | maintenance and spot improvement of Cherab ward roads | Upgrading the roads to ridable state | Ksh. 19,996,700.00 | 2020-01-15 | 2020-05-14 | Completed |
County | Completion and operationalization of Isiolo abattoir and feedlot | operationalization livestock infrastructure | Ksh. 550,000,000.00 | 2018-07-01 | 2022-06-30 | Ongoing |
County | Qiliisa - Sabarwawa Road | Upgrading the roads to ridable state | Ksh. 3,099,520.00 | 2020-01-15 | 2020-05-14 | Completed |
County | capacity development of county staff | Capacity building of staff and Development of policies | Ksh. 25.00 | 2021-07-01 | 2022-06-30 | Ongoing |
County | construction of vip toilet/latrine in VtcS- Uhuru Polytechnic | To establish basic sanitation facilities at ecde centres | Ksh. 750,000.00 | 2019-07-15 | 2020-12-14 | Completed |
Ward | Construction of social hall in Ngaremara | Ksh. 4.70 | 2021-09-23 | 2021-12-15 | Ongoing | |
County | Dambala Diiri - Qilisa Road | Upgrading the roads to ridable state | Ksh. 5,867,280.00 | 2020-01-15 | 2020-05-14 | Completed |
Ward | construction of social hall in Bisan Biliqo | Ksh. 4.80 | 2020-07-23 | 2020-11-27 | Completed | |
Ward | PWDs groups grant | Increase access to funds for vulnerable groups | Ksh. 6.00 | 2021-10-15 | 2021-12-15 | Planned |
County | Bulesa - Ilman Jillow Access Road | Upgrading the roads to ridable state | Ksh. 2,354,800.00 | 2020-01-15 | 2020-05-14 | Completed |
Ward | Protection and fencing of Public cemetery at Burat | Enhanced protection of public cemeteries | Ksh. 1,500,000.00 | 2021-03-08 | 2021-06-23 | Completed |
Ward | construction of ecde classroom | ecde classroom construction | Ksh. 24,000,000.00 | 2019-10-16 | 2020-04-15 | Completed |
County | maintenance of streetlights | Installation and maintenance of streetlight | Ksh. 1,600,000.00 | 2018-12-10 | 2019-02-28 | Completed |
County | Construction of fire station phase 1 | Construction of a fire station building | Ksh. 3,500,000.00 | 2019-01-08 | 2019-03-29 | Ongoing |
County | Biliqo Marara - Kuro Road | Upgrading the roads to ridable state | Ksh. 3,674,590.00 | 2020-01-15 | 2020-05-14 | Completed |
Ward | Dissemination and implementation of County Government policies | Public Barazas at Ward levels | Ksh. 10.00 | 2021-07-01 | 2022-06-30 | Ongoing |
Ward | Tree planting in Bassa Location. | Enhanced ecosystem productivity and sustainability | Ksh. 1,000,000.00 | 2021-02-08 | 2021-06-23 | Completed |
Ward | Establishment of Dumpsite in Garbatulla ward | Improved waste management and pollution control | Ksh. 2,000,000.00 | 2021-02-08 | 2021-06-23 | Completed |
Ward | Gubadida Irrigation Scheme | increase area under irrigation | Ksh. 35,000,000.00 | 2019-10-10 | 2021-06-16 | Ongoing |
County | Development of Disaster Information Management System | To Construct offices for the ward administrators | Ksh. 4,300,000.00 | 2021-02-01 | 2021-11-16 | Under Procurement |
County | Development of Communication Strategy | creation of the information database | Ksh. 3,000,000.00 | 2020-02-12 | 2021-05-18 | Pre Procurement |
County | DRM Policy Development | policy formulation and development | Ksh. 3,000,000.00 | 2020-05-12 | 2021-03-11 | Completed |
County | Governor's Releases dissemination | Coverage of all the Governors functions | Ksh. 50,000,000.00 | 2021-06-07 | 2022-03-07 | Ongoing |
County | Formation and Training of Monitoring Committees | Formation and training of Project Monitoring Committees | Ksh. 5,000,000.00 | 2021-07-12 | 2022-06-06 | Ongoing |
County | Coverage of Governor's Functions | Conduct training need analysis for the county staff | Ksh. 30,000,000.00 | 2021-07-05 | 2022-06-06 | Ongoing |
County | Development of reporting Systems | Develop good reporting systems | Ksh. 1,200,000.00 | 2021-09-20 | 2022-08-01 | Ongoing |
County | Monitoring of the Manifesto Performance | Develop good reporting systems | Ksh. 1,200,000.00 | 2021-09-20 | 2021-11-08 | Ongoing |
County | County Citizen Participation Fora | Develop good reporting systems | Ksh. 2,500,000.00 | 2021-11-15 | 2022-01-03 | Ongoing |
County | Monthly Field Visits | Formation and training of Project Monitoring Committees | Ksh. 400,000.00 | 2021-09-13 | 2021-10-04 | Ongoing |
Ward | Iresaboru pipeline rehabilitation | Enhancing water supply and storage | Ksh. 3,496,470.00 | 2021-05-10 | 2021-06-15 | Ongoing |
Ward | Rehabilitation of Rumate sand dam | Enhancing water supply and storage | Ksh. 1,962,260.00 | 2021-05-10 | 2021-06-15 | Ongoing |
Ward | Rehabilitation of Longopito sand dam | To enhance water supply for domestic and livestock use | Ksh. 1,994,130.00 | 2021-05-10 | 2021-06-15 | Ongoing |
Ward | Drilling of Arow borehole | Enhancing water supply and storage | Ksh. 3,496,470.00 | 2021-05-10 | 2021-06-15 | Completed |
Ward | Goda pipeline repair | Enhancing water supply and storage | Ksh. 2,981,080.00 | 2021-05-10 | 2021-06-15 | Completed |
Ward | Iresaboru laga 2 water works | Enhancing water supply and storage | Ksh. 4,998,300.00 | 2021-03-10 | 2021-06-30 | Completed |
Ward | Iresaboru borehole mechanized access bush clearing works | Enhancing water supply and storage | Ksh. 4,994,960.00 | 2021-03-10 | 2021-06-30 | Completed |
Ward | Iresaboru lagga I water works | Enhancing water supply and storage | Ksh. 4,976,680.00 | 2020-08-19 | 2020-08-19 | Completed |
Ward | Drilling of Quri borehole | Enhancing water supply and storage | Ksh. 3,862,800.00 | 2021-01-11 | 2021-02-08 | Terminated |
Ward | Installation of water meters in Kinna | Enhancing water supply and storage | Ksh. 2,994,050.00 | 2021-05-10 | 2021-06-10 | Completed |
Ward | Water trucking in Modogashe | Water trucking | Ksh. 3,000,000.00 | 2021-05-10 | 2021-06-10 | Completed |
Ward | Extension of LMD water supply | Enhancing water supply and storage | Ksh. 2,999,760.00 | 2021-05-10 | 2021-06-10 | Completed |
Ward | Water trucking In Belgesh and Titu | Water trucking | Ksh. 2,992,000.00 | 2020-09-30 | 2020-11-30 | Completed |
Ward | Water Trucking in Iresaboru | Water trucking | Ksh. 2,982,000.00 | 2020-09-30 | 2020-11-30 | Completed |
Ward | Water Trucking in Dogogicha,Lakole and Mataarba | Water trucking | Ksh. 2,970,000.00 | 2020-07-15 | 2020-09-15 | Completed |
Ward | Water trucking In Alango,Dakiye and Dadacha Basa | Water trucking | Ksh. 2,970,000.00 | 2020-07-15 | 2020-09-15 | Completed |
Ward | Repair of Mlango, Kalawash, Oldonyiro and Kambi Juu | Enhancing water supply and storage | Ksh. 2,951,120.00 | 2021-01-10 | 2021-01-30 | Completed |
Village | Repair of Bisan Biliqo,Yamicha and Korbesa | Enhancing water supply and storage | Ksh. 2,873,130.00 | 2021-05-10 | 2021-06-15 | Completed |
Village | Construction of Bulesa masonry ground tank | Enhancing water supply and storage | Ksh. 2,799,990.00 | 2021-04-10 | 2021-06-15 | Completed |
Ward | Provision for spares and repairs or Yakhbarsadi,Boji,Erimet and Belgesh Water Supplies | To enhance water supply foor domestic and livestock use | Ksh. 2,480,450.00 | 2020-10-15 | 2020-11-15 | Completed |
Ward | Repair of Kombola ,Modogashe and Ngalabilabia boreholes | Enhancing water supply and storage | Ksh. 2,474,260.00 | 2020-10-15 | 2020-11-15 | Completed |
Ward | Repair of Llengurma, , Ngarendare and Daaba boreholes | To enhance water supply for domestic use | Ksh. 2,434,290.00 | 2020-10-15 | 2020-11-15 | Completed |
Ward | Repairs in Matagari, Moggore and Garbatulla dispensary boreholeS | Enhancing water supply and storage | Ksh. 2,398,880.00 | 2020-10-15 | 2020-11-15 | Completed |
Ward | Repairs of Malkadaqa,Belgesh and Dogogicha water supplies | Enhancing water supply and storage | Ksh. 2,390,600.00 | 2020-10-15 | 2020-11-15 | Completed |
Ward | Repair of Toiboto, Dabasiti and Modogashe water supplies | Enhancing water supply and storage | Ksh. 2,357,790.00 | 2021-01-15 | 2021-03-15 | Completed |
Ward | Spares for repairs of Gafarsa and Toiboto boreholes | Enhancing water supply and storage | Ksh. 2,194,040.00 | 2021-01-15 | 2021-03-15 | Completed |
Ward | Repairs for Chumvi yare, Ksile and Bisan biliqo water supplies | Enhancing water supply and storage | Ksh. 2,183,890.00 | 2021-01-15 | 2021-03-15 | Completed |
Ward | Korbesa water project works | Enhancing water supply and storage | Ksh. 21,000,000.00 | 2020-10-05 | 2021-06-30 | Ongoing |
Ward | Repair of Duse ,Roqa and Merti water supplies | Enhancing water supply and storage | Ksh. 2,183,340.00 | 2021-01-15 | 2021-03-15 | Completed |
Sub County | Spares for Bertume and Bulesa boreholes | Enhancing water supply and storage | Ksh. 2,150,170.00 | 2020-09-01 | 2020-09-30 | Completed |
Ward | Repairs for Manyatta zebra, Daaba and Rapsu water supplies | Enhancing water supply and storage | Ksh. 1,934,900.00 | 2020-09-01 | 2020-09-30 | Completed |
Ward | Repairs for Kisile and Ngaremara boreholes | To enhance water supply for domestic use | Ksh. 1,848,000.00 | 2020-09-01 | 2020-09-30 | Completed |
Sub County | Water trucking in Belgesh and Titu in Garbatulla sub county | Water trucking | Ksh. 1,320,000.00 | 2020-09-01 | 2020-09-30 | Completed |
Sub County | Iresaboru borehole pipeline access route opening through mechanized means | To enhance water supply for domestic use | Ksh. 1,314,500.00 | 2020-08-15 | 2020-09-15 | Completed |
Sub County | Repair of Kotikore and Machalo boreholes | To enhance water supply for domestic and livestock use | Ksh. 890,000.00 | 2021-03-15 | 2021-03-30 | Completed |
Sub County | Walyana borehole repairs | Enhancing water supply and storage | Ksh. 851,000.00 | 2020-10-05 | 2020-12-05 | Completed |
County | capacity building of technical staff | Train and equip technical staff with the relevant and emerging technologies on fish production | Ksh. 500,000.00 | 2019-07-01 | 2020-06-30 | Completed |
County | Recruitment of fish farmers | to increase fish production | Ksh. 200,000.00 | 2020-07-15 | 2020-12-16 | Completed |
Ward | Revitalization and commercialization of Agriculture training centre (ATC) | To Improve institutional, effectiveness and efficiency. to enhance service delivery | Ksh. 100,000,000.00 | 2021-07-13 | 2022-06-14 | Planned |
Ward | Establish business incubation and innovation hub at ATC | to Increase income through Agriculture commercialization in smallholder farmers and off-farm sectors | Ksh. 100,000,000.00 | 2021-05-13 | 2022-06-30 | Planned |
Sub County | Devolved unit capacity development for Sub County Administrators | Devolved units capacity development vehicles for sub County Administrators | Ksh. 15,000,000.00 | 2019-07-01 | 2020-06-30 | Ongoing |
County | Establishment of child rescue centres in Isiolo , Oldonyiro and Garbatulla | To provide assistance to the vulnerable child | Ksh. 45,000.00 | 2019-06-10 | 2022-08-09 | Planned |
Sub County | Guidance and counselling centres/ countywide | To provide requisite assistance to the vulnerable members of the community | Ksh. 30,000,000.00 | 2019-09-05 | 2022-12-12 | Planned |
County | Developing bulk sms system | To provide an efficient and effective channel for information between and within county government and the people | Ksh. 500,000.00 | 2019-10-08 | 2020-10-12 | Completed |
County | Development of County Optimal staff establishment | Development of county staff establishment | Ksh. 6,000,000.00 | 2019-07-01 | 2020-06-30 | Completed |
County | Creating and managing Governor's Delivery Unit social media pages | To create visibility on governor's projects. | Ksh. 200,000.00 | 2019-06-03 | 2019-12-10 | Ongoing |
County | Establish county quarterly and weekly e-bulletin | To create visibility on governor's projects. | Ksh. 10,000,000.00 | 2019-06-04 | 2022-06-20 | Ongoing |
County | Peace Building and conflict Resolution | conflict prevention, management and Resolution | Ksh. 10,000,000.00 | 2019-07-01 | 2020-06-30 | Ongoing |
County | Capacity building for industrial development across the county | capacity building conducted for the community on industrial development | Ksh. 11,100,000.00 | 2019-08-14 | 2020-06-22 | Ongoing |
County | Development of county cooperative act | county cooperative act developed | Ksh. 4.00 | 2018-06-01 | 2019-06-30 | Ongoing |
County | Governance and accountability of cooperative societies in the county | training of society members on management | Ksh. 2,000,000.00 | 2019-09-03 | 2020-06-08 | Ongoing |
County | Awareness campaigns and trainings across the county | traders and general public trained on consumer rights | Ksh. 2,000,000.00 | 2020-04-15 | 2020-06-22 | Ongoing |
County | Compliance in weighing and measuring in schools | weighing and measuring instruments verified and procured in schools | Ksh. 10.00 | 2019-09-09 | 2022-11-22 | Planned |
County | Procurement of weight and measures standards for office use | weights and measures standard procured | Ksh. 10.00 | 2018-08-14 | 2022-06-15 | Ongoing |
County | Profiling of business producer groups and market linking across the county | profiling of products groups for export | Ksh. 2,000,000.00 | 2019-08-21 | 2020-06-15 | Ongoing |
County | Ease of doing business survey in the county | survey for locally available resources for trade conducted, trained entrepreneurs skills and knowledge on business management and environment | Ksh. 2,000,000.00 | 2020-05-18 | 2021-05-18 | Completed |
County | Enterpreneur management training to MSME operators in the county | Training and capacity building for traders | Ksh. 0.00 | 2018-07-01 | 2022-06-30 | Ongoing |
County | Rehabilitation of isiolo holding ground | To rehabilitate isiolo holding ground | Ksh. 10,000,000.00 | 2019-07-01 | 2020-05-06 | Ongoing |
County | Rehabilitation of rangelands | To manage and rehabilitate rangelands | Ksh. 3,000,000.00 | 2019-05-02 | 2020-05-06 | Ongoing |
Ward | Redesign the intake structure | increase area under irrigation | Ksh. 20,000,000.00 | 2021-07-14 | 2022-06-30 | Planned |
Ward | New dispensaries at Dima Ado, Biliqi, Mogore, Yaqbarsadi, Rumate, Longopiti, Nkorika, Parkuruk, Mogore & Awarsitu | To increase access to health services | Ksh. 60,000,000.00 | 2018-07-01 | 2022-06-30 | Ongoing |
Ward | changing water pumping from diesel to solar | reduce the cost of irrigation by changing from diesel to solar power | Ksh. 20.00 | 2021-07-08 | 2022-06-30 | Planned |
County | Rehabilitation of circuit Road from Ngaremare gate to Simba Lodge to Revitalize tourist circuit | To increase tourists arrivals and earnings for the County’s Economic Development | Ksh. 4,000,000.00 | 2018-02-01 | 2022-07-05 | Completed |
County | Modogashe – Kuri Road | To improve road transport access to essential services | Ksh. 64,000,000.00 | 2018-08-07 | 2019-05-21 | Completed |
County | Fororsha – Modogashe road | To improve road transport access to essential services | Ksh. 92,000,000.00 | 2018-10-09 | 2019-01-09 | Completed |
County | Street naming and road signage | To improve management of county towns | Ksh. 14,000,000.00 | 2020-05-12 | 2020-10-20 | Completed |
County | Leparua – Lotik – Shamabani Alamach Road | Upgrading the roads to paved standard | Ksh. 35,000,000.00 | 2018-09-03 | 2019-07-08 | Completed |
County | Appointment of committee members | To improve management of county towns | Ksh. 5,000,000.00 | 2019-09-24 | 2019-11-27 | Completed |
County | Operationalization of Bisan adhi national reserve | Increased County Esteem and Investor Confidence | Ksh. 440,000,000.00 | 2018-02-01 | 2022-05-05 | Ongoing |
County | Develop institutional development strategy | To improve management of county towns | Ksh. 10,000,000.00 | 2019-03-19 | 2019-10-16 | Completed |
County | Establishment of town management committees | To improve management of county towns | Ksh. 80,000,000.00 | 2019-02-05 | 2019-06-04 | Completed |
Sub County | Construction of pediatric ward at Oldonyiro | To increase access to pediatric services | Ksh. 10,000,000.00 | 2018-07-01 | 2022-06-30 | Planned |
Sub County | Construction of pediatric ward at Oldonyiro | To increase access to pediatric services | Ksh. 10,000,000.00 | 2018-07-01 | 2022-06-30 | Planned |
County | Aremet- Lorukpo-Leparua – Budalnga Road | To construction accessibility roads by gravelling patching | Ksh. 46,000,000.00 | 2018-07-09 | 2019-06-25 | Completed |
County | Installation of radio communication network in the national reserves in the county | To improve communication and security in the parks | Ksh. 10,000,000.00 | 2018-03-01 | 2019-11-06 | Completed |
County | Increasing access to farming grants | Community driven support Initiative for food security and increased income in all wards | Ksh. 50.00 | 2018-07-01 | 2022-06-30 | Ongoing |
County | Development of urban investment plan | To improve management of Isiolo municipality | Ksh. 200,000,000.00 | 2018-03-12 | 2019-04-08 | Completed |
County | Improvement of national reserves management | To increase collected revenue from parks | Ksh. 200,000,000.00 | 2018-02-01 | 2020-07-03 | Completed |
Ward | Health staff houses at Noloroi, Gotu, Kulamawe, Barambate, Gubatu, Kone, Eldera, Badana, Duse, Biliqi Nur & Boji | To improve accommodation of rural health facilities' personnel | Ksh. 30,000,000.00 | 2018-07-01 | 2022-06-30 | Ongoing |
County | Setting up of offices | To improve management of Isiolo municipality | Ksh. 15,000,000.00 | 2018-05-16 | 2018-12-18 | Completed |
County | Support to county wildlife conservation and compensation committee | Reduce the impact of animals encroachment to human settlements and farms | Ksh. 10,000,000.00 | 2018-02-01 | 2022-06-03 | Ongoing |
County | Renal unit | To increase access to health service | Ksh. 100,000,000.00 | 2018-07-01 | 2021-06-30 | Completed |
County | Farmers training | Community driven support Initiative for food security and increased income in all wards | Ksh. 5.50 | 2018-07-01 | 2022-06-30 | Ongoing |
County | Appointment of board members | To improve management of Isiolo municipality | Ksh. 4,000,000.00 | 2018-08-14 | 2018-11-05 | Completed |
County | Badana-Modogashe | Upgrading the roads to paved standard | Ksh. 92,000,000.00 | 2018-08-07 | 2019-06-25 | Completed |
County | Public education on wildlife conservation management 2013 | To enhance harmonious co-existence between humans and wild animals | Ksh. 10,000,000.00 | 2018-05-01 | 2022-07-03 | Ongoing |
County | Fish post harvest management | To reduce post harvest losses | Ksh. 2,000,000.00 | 2019-05-02 | 2020-05-06 | Ongoing |
County | Declaration of Isiolo Municipality through the charter | To improve management of Isiolo municipality | Ksh. 3,000,000.00 | 2020-12-15 | 2021-03-16 | Completed |
County | Community conservancy development and management at Cherab Ward namely along Lakole, Duma, Dogogicha Yamicha | To improve natural and wildlife resources protection, security and community involvement | Ksh. 300,000,000.00 | 2018-03-01 | 2022-07-03 | Ongoing |
County | Drafting of Isiolo Municipality Charter | To improve management of Isiolo municipality | Ksh. 70,000,000.00 | 2020-01-14 | 2020-11-10 | Completed |
Ward | Gotu Dispensary | To increase access to health service | Ksh. 8,000,000.00 | 2018-07-01 | 2021-06-30 | Completed |
County | Formulate development controls | To formulate plans to guide management of urban spaces | Ksh. 5,000,000.00 | 2019-07-19 | 2022-07-12 | Ongoing |
County | Procurement of 10No. Motorcycles | County extension support service and capacity advancement | Ksh. 1,200,000.00 | 2020-07-01 | 2022-07-30 | Ongoing |
Ward | Completion of Oldonyiro irrigation scheme | increase area under irrigation | Ksh. 300,000,000.00 | 2020-07-10 | 2022-07-10 | Planned |
County | Develop town Spatial Plans | To formulate to guide management of urban spaces | Ksh. 5,000,000.00 | 2018-05-15 | 2020-05-12 | Completed |
County | Development of urban development plan | To formulate plans to guide management of urban spaces | Ksh. 50,000,000.00 | 2019-04-02 | 2021-05-05 | Completed |
County | Production of marketing documentary film, snap shots, booklets/flyers, marketing material for county investment potentials produced, identification of potential social and economic investors | To improve Partnership & Donor Coordination | Ksh. 10,000,000.00 | 2019-02-13 | 2020-06-22 | Ongoing |
County | Veterinary public health | to improve meat hygiene at isiolo slaughterhouse | Ksh. 1,000,000.00 | 2019-07-01 | 2020-06-30 | Ongoing |
County | Child Play | To enhance play and learning at the centres | Ksh. 4,000,000.00 | 2021-02-10 | 2021-03-10 | Planned |
County | Development of New conservancies | Enhanced tourism in the county | Ksh. 400,000,000.00 | 2018-05-01 | 2019-03-03 | Planned |
County | Development of New conservancies in Sericho, Garbatulla and Kina | Enhanced tourism in the county | Ksh. 30,000,000.00 | 2018-05-01 | 2022-03-03 | Ongoing |
County | Purchase of 2No. vehicles | County extension support service and capacity advancement | Ksh. 0.00 | 2020-07-01 | 2022-06-30 | Planned |
Ward | Completion of Oldonyiro irrigation scheme | increase area under irrigation | Ksh. 300,000,000.00 | 2019-07-10 | 2022-06-30 | Planned |
County | Construction, equipping and staffing at the office of the Governor | To improve management and storage of county records | Ksh. 70,000,000.00 | 2019-04-01 | 2020-05-05 | Completed |
County | Hiring of additional staff | County extension support service and capacity advancement | Ksh. 1,000,000.00 | 2018-07-01 | 2022-06-30 | Ongoing |
County | Construction of office block and installation of M&E systems recruitment of new staff formation of committees ,purchase of 4 vehicles | To Enhance implementation of the CIDPs | Ksh. 80,000,000.00 | 2019-01-02 | 2020-04-06 | Completed |
County | Construction of two residential compound | To provide conducive environment for executive | Ksh. 100,000,000.00 | 2018-04-17 | 2019-08-06 | Completed |
County | Community driven support Initiative for food security and increased income in all wards | To support community driven food security initiative | Ksh. 100,005,000.00 | 2019-07-10 | 2020-06-14 | Completed |
County | Bula Pesa Dispensary | To increase access to health services | Ksh. 8,000.00 | 2019-07-01 | 2021-06-30 | Ongoing |
County | Crop production improvement- county wide | Promotion of climate smart agriculture farming technologies | Ksh. 100,000,000.00 | 2018-07-11 | 2022-06-30 | Ongoing |
County | Medical products distribution (Procurement of a lorry and pick-up) | Logistical support for medical products distribution | Ksh. 20,000,000.00 | 2021-07-01 | 2022-06-30 | Planned |
County | Lenguruma Dispensary | To increase access to health service | Ksh. 8,000,000.00 | 2021-06-30 | 2022-06-30 | Planned |
County | Fencing of VTCs | Fence construction around VTCs | Ksh. 2,500,000.00 | 2020-02-10 | 2020-06-10 | Completed |
County | Water Tanks for VTCs | Water connection established | Ksh. 3,000,000.00 | 2020-04-08 | 2021-05-20 | Completed |
County | County Agricultural mechanization promotion services | To Increase acreage under crops and improve efficiency of farm operations | Ksh. 300,000,000.00 | 2018-07-10 | 2022-06-30 | Ongoing |
Ward | Construction of liner ponds | To increase fish production | Ksh. 300,000.00 | 2019-05-02 | 2020-05-06 | Completed |
County | VTCs Equipment | equip VTCs | Ksh. 4,000,000.00 | 2018-04-04 | 2018-04-04 | Completed |
County | VTC instructors development | VTC instructors recruitment | Ksh. 10,000,000.00 | 2021-02-10 | 2021-03-10 | Ongoing |
County | Gender mainstreaming and empowerment policies | Ksh. 100,000,000.00 | 2018-09-10 | 2022-08-29 | Ongoing | |
County | Construction of VTCs | Establishment of VTC facilities | Ksh. 26,000,000.00 | 2018-03-08 | 2018-12-19 | Completed |
Ward | Train Rapsu farmers on farming and agribusiness skills | increase area under irrigation | Ksh. 500,000.00 | 2019-07-01 | 2022-06-30 | Ongoing |
County | Establishment of small irrigation units countywide with water efficient technologies | To improve food and nutrition security by increasing crop acreage | Ksh. 20,000,000.00 | 2018-07-06 | 2022-06-30 | Ongoing |
County | child protection | to discourage early marriage and other harmful cultural practices | Ksh. 1,000,000.00 | 2021-02-10 | 2021-03-10 | Planned |
County | Training of Women in productive businesses | Reduced gender inequality at all levels of development | Ksh. 20,000,000.00 | 2018-07-23 | 2022-11-14 | Ongoing |
Ward | Lining of 2.5km of water canals in Rapsu irrigation | increase area under irrigation | Ksh. 6,000,000.00 | 2019-07-01 | 2021-06-30 | Ongoing |
County | Enterprise Development fund | Reduce gender inequality at all levels of development | Ksh. 200,000,000.00 | 2018-08-08 | 2022-05-09 | Planned |
County | Noloroi Dispensary | To improve access to health services | Ksh. 5,000,000.00 | 2018-07-01 | 2022-06-30 | Ongoing |
Ward | Change of energy from diesel to solar power in Iresaboru irrigation scheme | increase area under irrigation | Ksh. 0.00 | 2021-07-01 | 2022-06-30 | Planned |
Ward | Rehabilitation and expansion of Bulesa irrigation scheme in Chari ward | To improve food and nutrition security by increasing crop acreage | Ksh. 50,000,000.00 | 2020-07-14 | 2022-06-30 | Ongoing |
Ward | Train famers on farmers on farm management skills | To improve farmers agronomic practices | Ksh. 3,200,000.00 | 2021-07-01 | 2022-07-30 | Planned |
County | County Public Participation | Public Participation | Ksh. 10,000,000.00 | 2019-07-01 | 2020-06-30 | Ongoing |
Ward | Iresaboru irrigation scheme expansion | To open up more land for cultivation under irrigation | Ksh. 0.00 | 2020-07-01 | 2022-06-30 | Planned |
County | provision of preschool meals | provision of feeding program | Ksh. 10,000,000.00 | 2021-02-10 | 2021-05-20 | Ongoing |
County | Land survey | Development of Local Physical Plans (LPDP) | Ksh. 60,000,000.00 | 2019-07-05 | 2022-06-15 | Ongoing |
Ward | Completion of Bisan Biliqo irrigation in Chari Ward | To improve food and nutrition security by increasing crop acreage | Ksh. 50,000,000.00 | 2019-07-08 | 2022-07-06 | Planned |
County | Construction of recycle plans | To enhance Garbage collection in Isiolo town | Ksh. 50,000,000.00 | 2019-03-05 | 2022-01-11 | Under Procurement |
County | Gachuru – Gotu – Merti Road | Improve the roads to access essential services | Ksh. 50,000,000.00 | 2018-07-09 | 2019-06-25 | Completed |
County | Procurement of garbage collection vehicle units | To enhance garbage collection in Isiolo town | Ksh. 60,000,000.00 | 2018-06-19 | 2022-08-02 | Completed |
County | Purchase of ECDE furniture | ecde appropriate furniture provision | Ksh. 4,000,000.00 | 2021-02-10 | 2021-05-20 | Ongoing |
County | Garbatulla paediatric ward | To increase access to infant health care services | Ksh. 6,000,000.00 | 2018-07-01 | 2022-06-30 | Ongoing |
County | Installation of high masts and electrical works | To reduce night insecurity and improve night trade | Ksh. 50,000,000.00 | 2018-06-12 | 2022-09-08 | Completed |
Ward | Rehabilitation and expansion of Malka Daka irrigation in Garba Tulla ward | To improve food and nutrition security by increasing crop acreage | Ksh. 50,000,000.00 | 2019-06-04 | 2022-07-13 | N/A |
County | Isiolo county investors conference | trade fair, exhibitions and talks conducted | Ksh. 2,000,000.00 | 2022-03-07 | 2022-03-21 | Planned |
County | Livestock Restocking | To mitigate challenges of drought in the county | Ksh. 3,000,000.00 | 2019-05-02 | 2020-05-06 | Terminated |
County | Biodiversity survey for plants and animals at National Reserves(Shaba, Buffalo Springs, | To identify ecology on vegetation and wildlife available in the National Reserve | Ksh. 100,000,000.00 | 2018-03-01 | 2019-02-01 | Completed |
County | Baraza park social ground in Isiolo town | To harness relationship and promote cohesion | Ksh. 10,000,000.00 | 2018-11-05 | 2022-09-15 | Ongoing |
County | Installation of street lights and electrical works | To improve night business and security | Ksh. 135,000,000.00 | 2018-05-23 | 2022-08-01 | Completed |
County | isiolo county education bursary | Education bursary establishment | Ksh. 35,000,000.00 | 2018-03-08 | 2018-04-04 | Completed |
County | Refurbishment/renovation of Isiolo County Hospital | To improve Hospital physical infrastructure | Ksh. 100,000,000.00 | 2018-06-01 | 2020-12-31 | Completed |
County | Establishment of human-wildlife conflict solution centre in the county | To reduce human-wildlife conflict | Ksh. 100,000,000.00 | 2018-03-01 | 2019-05-25 | Completed |
County | Construction of Isiolo Stadium phase 1 | IMPROVE SPORTS INFRASTRUCTURE IN THE COUNTY | Ksh. 130,000,000.00 | 2018-06-05 | 2019-06-15 | Ongoing |
County | Establishment of cultural artefacts centre | Enhancing heritage and culture knowledge, appreciation and conservation | Ksh. 45,000,000.00 | 2018-09-17 | 2022-10-11 | Planned |
County | Maintenance of governance houses and offices | To provide low cost quality housing | Ksh. 50,000,000.00 | 2018-02-06 | 2022-08-08 | Ongoing |
Ward | Completion of Oldonyiro irrigation scheme | To improve food and nutrition security | Ksh. 500,000,000.00 | 2019-07-17 | 2022-06-30 | Planned |
County | Conserve and monitor threatened species | To increase population of endangered species | Ksh. 100,000,000.00 | 2018-03-01 | 2022-07-03 | Ongoing |
County | Establishment of QAS office | Quality assurance and Standards office Established | Ksh. 3,000,000.00 | 2018-05-08 | 2018-05-09 | Completed |
County | Installation of sewerage systems | To improve the urban dwellers access to better social amenities | Ksh. 10,000,000.00 | 2018-07-20 | 2022-10-25 | Completed |
County | procurement of weights and measures standards for office use | weighing and measuring instruments verified and procured in schools | Ksh. 100,000,000.00 | 2019-09-10 | 2022-06-15 | Completed |
County | Cash transfer programme | Reduce gender inequality at all levels of development | Ksh. 400,000,000.00 | 2018-08-06 | 2022-08-26 | Planned |
County | Park transport management support | Improve security for the county’s national reserves | Ksh. 60,000,000.00 | 2018-02-01 | 2020-07-03 | Completed |
County | Installation of clean piped water to households | To improve the urban dwellers access to better social amenities | Ksh. 10,000,000.00 | 2018-01-10 | 2022-02-14 | Ongoing |
County | Baseline survey on assets, equipment, human resource and investments determined. | To enhance tourism in the county | Ksh. 5,000,000.00 | 2018-02-01 | 2018-12-01 | Completed |
County | County culture and art support | To improve heritage and culture awareness, knowledge, appreciation and conservation | Ksh. 5,000,000.00 | 2017-08-22 | 2022-12-08 | Ongoing |
County | Construction of parks and social halls | To improve the urban dwellers access to better social amenities | Ksh. 50,000,000.00 | 2018-04-10 | 2022-05-16 | Under Procurement |
County | Oxygen plant in Isiolo, Garbatulla and Merti Hospitals | Set up and operationalize medical training centres in the County | Ksh. 35,000,000.00 | 2018-06-01 | 2022-06-30 | Ongoing |
County | SNE teacher employment | Ecde teachers employment | Ksh. 3,000,000.00 | 2021-05-25 | 2021-06-24 | Ongoing |
County | Review management plan for national reserves | To enhance tourism in the county | Ksh. 5,000,000.00 | 2018-03-01 | 2018-09-02 | Completed |
County | Chumviyale – Akunoit Road | Construction of accessible roads | Ksh. 24,000,000.00 | 2018-10-09 | 2019-12-12 | Ongoing |
County | Construction of low cost housing units | Construction& Maintenance of housing units | Ksh. 200,000,000.00 | 2019-03-12 | 2022-02-15 | Pre Procurement |
County | ECDE teachers development | Ecde teachers employment | Ksh. 25,000,000.00 | 2021-05-24 | 2021-06-24 | Ongoing |
County | Disaster management in the national reserves | To enhance tourism in the county | Ksh. 250,000,000.00 | 2018-02-01 | 2022-06-03 | Ongoing |
County | Construction of recreational parks | To provide social amenities | Ksh. 100,000,000.00 | 2018-09-05 | 2022-08-09 | Under Procurement |
County | Health facility institutional support (Infrastructure and equipping) | To improve health service performance | Ksh. 100,000,000.00 | 2018-06-01 | 2022-06-30 | Ongoing |
County | Planting flowers and plants | Landscaping of urban area | Ksh. 50,000,000.00 | 2019-08-13 | 2022-05-18 | Planned |
County | Private sector investment encouragement in tourism | To enhance tourism in the county | Ksh. 0.00 | 2018-05-01 | 2022-07-03 | Planned |
County | profiling of business producer groups and market linking across the county | To increase wealth creation for local producer groups | Ksh. 2.00 | 2019-09-09 | 2020-12-14 | Ongoing |
County | Branded tourism Tourism Bus | Enhanced tourism in the county | Ksh. 15,000,000.00 | 2018-07-01 | 2019-06-06 | Completed |
County | Procurement of fire fighting engines | To improve safety of citizens | Ksh. 100,000,000.00 | 2018-07-17 | 2022-06-14 | Under Procurement |
County | Medical product distribution (Purchase of a 10 ton lorry and a pick-up) | Logistical support for medical products distribution | Ksh. 20,000,000.00 | 2021-07-01 | 2022-06-30 | Ongoing |
County | Establishment of 2 unit conservancies | Increased Diversity in Tourism Products | Ksh. 10,000,000.00 | 2019-05-01 | 2020-07-03 | Planned |
County | Kiutene-Murera- Kinna –Garbatulla Road | To improve road transport access to essential services | Ksh. 48,000,000.00 | 2018-05-03 | 2019-05-21 | Completed |
County | Face lifting of park entry gates Ngaremara and Chokaa gates, | To enhance tourism in the county | Ksh. 1,100,000.00 | 2019-05-01 | 2020-07-03 | Completed |
County | Hiring of staff | To improve service delivery | Ksh. 100,000,000.00 | 2020-02-12 | 2022-08-10 | Ongoing |
County | support of youth groups | IMPOROVE SPORTS INFRASTRUCTURE IN THE COUNTY | Ksh. 8,000,000.00 | 2020-06-15 | 2021-06-15 | Ongoing |
County | Establishment of cultural centre | Enhancing heritage and culture knowledge, appreciation and conservation | Ksh. 50,000,000.00 | 2019-07-02 | 2020-05-21 | Planned |
County | youth empowerment project | to ensure an increased participation of youth in county development | Ksh. 5,000,000.00 | 2019-06-15 | 2020-06-15 | Ongoing |
County | Picnic sites development at Shaba (2), buffalo springs (3), Simba, Ashnil, Serena | To enhance tourism in the county | Ksh. 0.00 | 2018-08-01 | 2021-02-05 | Planned |
County | Construction of fire station building | To improve safety of people | Ksh. 100,000,000.00 | 2019-04-10 | 2022-05-18 | Ongoing |
County | Electronic medical record installation at Isiolo and Garbatulla Hospitals | To increase efficiency and quality of health care | Ksh. 20,000,000.00 | 2020-05-01 | 2021-04-01 | Completed |
County | Improvement of roads and airstrip networks in the national reserves (Shaba) | To enhance tourism in the county | Ksh. 70,000,000.00 | 2018-03-01 | 2021-08-05 | Ongoing |
County | Renovation and branding of offices at complex | To enhance tourism in the county | Ksh. 10,000,000.00 | 2018-01-01 | 2018-12-01 | Completed |
County | Equipping of health facilities with ICT equipment (Computers, servers and networks) | To increase access to specialized services | Ksh. 50,000,000.00 | 2020-07-01 | 2021-06-30 | Ongoing |
County | strengthening of Fish Safety Assurance, Value Addition and Marketing | To increase fish consumption per capita per year and income from fish and fishery product | Ksh. 100,000.00 | 2019-07-02 | 2020-06-30 | Ongoing |
County | Construction of cabros | Cabro paving in identified car park space | Ksh. 100,000,000.00 | 2020-05-20 | 2021-05-12 | Completed |
County | Renovation of security staff houses at complex, Naturbi | To enhance tourism in the county | Ksh. 3,100,000.00 | 2018-05-01 | 2019-04-03 | Ongoing |
County | Housing and sanitation for rangers renovated | Increased County Esteem and Investor Confidence | Ksh. 3,100,000.00 | 2018-02-01 | 2020-02-05 | Completed |
County | Tourism legal framework development | To enhance tourism in the county | Ksh. 15,000,000.00 | 2018-03-01 | 2022-05-03 | Ongoing |
County | Development of a harmonized tourism and wildlife policy | To enhance tourism in the county | Ksh. 7,000,000.00 | 2018-05-01 | 2022-07-03 | Ongoing |
County | Promote Management and Development of Capture Fisheries | To increase food security and income levels of small holder farmers | Ksh. 300,000.00 | 2019-07-01 | 2020-06-30 | Ongoing |
County | Park Roads maintenance Grading and Gravel Patching from Ngaremara Gate to Simba lodge and Airstrip | To enhance tourism in the county | Ksh. 3,900,000.00 | 2018-05-01 | 2022-07-03 | Completed |
County | Construction of KMTC classrooms (study classroom at ICTRH) | Set up and operationalize medical training centres in the County | Ksh. 15,000,000.00 | 2020-07-01 | 2021-06-30 | Completed |
Flagship | Isiolo Modern Market- Phase I | Construction of modern market | Ksh. 545,000,000.00 | 2019-05-08 | 2020-06-19 | Ongoing |
Ward | construction of Ngaremara perimeter wall | To promote trade, broaden internal base and market | Ksh. 5,000,000.00 | 2018-08-07 | 2019-02-12 | Completed |
County | Research and survey | To enhance research and surveys | Ksh. 3,000,000.00 | 2020-05-04 | 2021-05-04 | Ongoing |
County | Institute countywide baseline surveys to support M&E | To enhance provision of overall policy formulation, planning, budgeting, | Ksh. 60,000,000.00 | 2018-02-01 | 2022-07-03 | Ongoing |
County | livestock vaccination | To attain 80% livestock vaccination | Ksh. 6,000,000.00 | 2019-07-01 | 2020-06-30 | Ongoing |
County | Automation of M&E activities | Development of integrated reporting systems | Ksh. 5,000,000.00 | 2018-05-31 | 2022-05-31 | Ongoing |
County | Rehabilitation of Garba Tulla market | need assessment study, training and capacity building for traders, linkages to financial institution, market and other legal institutions eg KEBS | Ksh. 2.00 | 2019-01-08 | 2019-06-10 | Completed |
County | Development of County Sector Plans and policies | To enhance planning &budgeting formulation | Ksh. 100,000,000.00 | 2017-07-02 | 2022-06-03 | Ongoing |
County | Projects' Monitoring | Formation and training of Project Monitoring Committees | Ksh. 8,000,000.00 | 2019-08-05 | 2022-06-06 | Ongoing |
County | Development and modernisation of Isiolo County Information and documentation centre ICIDC | To enhance county information access | Ksh. 50,000,000.00 | 2020-02-01 | 2022-03-03 | Ongoing |
Ward | Construction of offices at ward levels | To Construct offices for the ward administrators | Ksh. 23,500,000.00 | 2019-07-01 | 2020-06-30 | Ongoing |
County | ECDE Classrooms | ecde classroom construction | Ksh. 12,000,000.00 | 2021-05-24 | 2021-06-24 | Planned |
County | Isiolo county Revenue Automation | Improvement of county own revenue performance | Ksh. 30.00 | 2018-01-10 | 2021-02-16 | Completed |
County | Development of M&E policy | To enhance provision of overall policy formulation, planning, budgeting, strategic direction for the socio-economic transformation of the country and implementation of the CIDP | Ksh. 10,000,000.00 | 2020-07-02 | 2021-05-05 | Completed |
Flagship | Expansion of kilimani Gama Galana irrigation in Burat ward | To improve food and nutrition security | Ksh. 391,000,000.00 | 2019-05-02 | 2020-05-06 | Ongoing |
County | Establishment of county statistical office | To enhance of County integrated planning | Ksh. 3,000,000.00 | 2020-07-02 | 2022-03-03 | Ongoing |
County | Developing County Public Participation Policy | Public Participation | Ksh. 4,000,000.00 | 2019-07-01 | 2020-06-30 | Completed |
County | Monitoring and Evaluation Reporting Appraisal systems | To enhance County Monitoring & Evaluation | Ksh. 10,000,000.00 | 2020-07-02 | 2021-05-05 | Ongoing |
County | Conducting county training need analysis | Conduct training need analysis for the county staff | Ksh. 4,500,000.00 | 2019-07-01 | 2020-06-30 | Completed |
County | Drought early warning system | Conduct bi-annual food security assessments | Ksh. 700,000.00 | 2020-07-01 | 2021-06-30 | Ongoing |
County | completion and operationalization of livestock market | To improve market access and enhance livelihoods | Ksh. 2,000,000.00 | 2019-07-01 | 2020-06-30 | Ongoing |
County | Training of Accountants | to improve service delivery | Ksh. 500,000.00 | 2017-11-05 | 2018-11-06 | Ongoing |
County | Isiolo County Revenue Automation | To increase local revenue for improved service delivery | Ksh. 30,000,000.00 | 2020-07-15 | 2021-06-15 | Completed |
Flagship Project | Programme | Objective | Planned start date | Planned end date |
---|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|
|
![]() |
|
Kiorbesa-Saleti-Mataarba cluster water supply system |
Date : 2021-08-19 01:08:12 |
a) Problem |
|
![]() |
|
Gubadida irrigation scheme. |
Date : 2021-09-06 04:09:36 |
Gubadida irrigation scheme was developed for the purpose of enabling 180 farmer to get adequate and equitable water to irrigate an average of half an acrea per houshold leading to a total of 36 Ha, however the available land can accomodate up to 100Ha.The phase one project component: Intake -sedimentation,pit,weir and fencing Main canal-1800m,10 division boxes for 10 secondary canals Farm access-10 culverts, 6 farm roads.Water troughs for livestock use.Solar powered shallow well with 5,000l tank for domestic water use. |
|
![]() |
|
Kilimani Dam : Longitude 0336228E UTM, Latitude 001348N UTM |
Date : 2021-09-07 09:09:23 |
Kilimani dam of capacity of 103000m3 in Burat Ward. The dam is serving Kilimani Game Galana irrigation scheme targeting 100Ha with 500 beneficiaries irrigating 0.25 acrea farm. Components of the project: 1)Excavation of the dam- with the capacity of 103000m3 2) Check dam- 1km long. 3)establishment of Kilimani Game Galana irrigation scheme. |
|
![]() |
|
Isiolo County Modern Market |
Date : 2021-09-07 01:09:10 |
Second phase Construction of the State of the Art Isiolo County Modern Market at a general status of 80% Complete. |
|
![]() |
|
Fire Engine |
Date : 2021-09-07 01:09:58 |
The County purchased fire engines that has helped curb disasters in the 3 wards of Municipality |
|
![]() |
|
Isiolo KMTC Hostels |
Date : 2021-09-07 01:09:23 |
Complete Construction of KMTC Classrooms at Isiolo Campus |
|
![]() |
|
Isiolo County Assembly Headquarters |
Date : 2021-09-07 01:09:46 |
85% construction of Isiolo County Assembly Headquarters at Isiolo Town |
|
![]() |
|
State of the Art County Government Headquarters, Isiolo County |
Date : 2021-09-07 01:09:13 |
60% Construction of State of the Art Isiolo County Executive Headquarters |
|
![]() |
|
Gubadida irrigation scheme, N 410098'8, E 33423'16 |
Date : 2021-09-07 02:09:30 |
Gubadida irrigation scheme was developed for the purpose of enabling 180 farmer to get adequate and equitable water to irrigate an average of half an acrea per houshold leading to a total of 36 Ha, however the available land can accomodate up to 100Ha.The phase one project component: Intake -sedimentation,pit,weir and fencing Main canal-1800m,10 division boxes for 10 secondary canals Farm access-10 culverts, 6 farm roads.Water troughs for livestock use.Solar powered shallow well with 5,000l tank for domestic water use. |
|
![]() |
|
SIGNING OF ENTERPRISE DEVELOPMENT FUND ACT BY H.E GOVERNOR KUTI |
Date : 2021-09-08 05:09:45 |
The signing of the EDF Act by his excellency the Governor on 23rd August 2021 brought a lot of joy to the vulnerable groups who have been patiently and eagerly waiting for this act to be signed so that the funds can be disbursed.The fund would economically empower youths,women and persons with disabilities as it is interest free loan and can be repaid in a grace period of two years.This interest free loan would boost the startup business and help this vulnerable groups to uplift themselves out of poverty . This EDF Act was such a great milestone for the department. |